Monday, December 16, 2019
Worlds First Precast Network Arch Bridge
Worlds First Precast Network Arch Bridge Worlds First Precast Network Arch Bridge As the bridge industry moves toward accelerated construction and precast components, the city of Fort Worth, TX, is ahead of the game with the worlds first precast-concrete network-arch bridge at a city gateway across the Trinity River.The bridge, which welches designed by the Texas Department of Transportation and is being built by Tempe, AZ-based Sundt Construction, is scheduled to be completed this fall.The innovative design and construction came about when the City of Fort Worth approached the Texas Department of Transportation for help in replacing a 100-year-old bridge across a popular thoroughfare connecting downtown to a cultural district. Fort Worth wanted a landmark that would be aesthetically pleasing and would make an impressive statement to motorists and pedestrians in the area. But the city also wanted to make sure during construction there was min disruption of traffic across the bridge a nd throughout surrounding streets where commercial and retail development arejust getting up and running.A Good SolutionTxDot engineers came up with the idea of marrying two types of bridge construction to meet Fort Worths requirements a network-arch bridge and a precast-concrete bridge. A network-arch bridge is architecturally interesting but typically made of more costly steel and because it is built in place, it causes more disruption of traffic a precast-concrete bridge, although not as aesthetically pleasing, is more economical, quicker to build, and requires much less lane closure time because the major components are built off-site.This is a very innovative idea, says Chris Cedar, Sundt civil group Texas area manager and the bridge project manager. Considering what Forth Worth was looking for, This seemed to be a good solution.The bridge is a series of 12 post-tensioned concrete arches, six on each side, which are the main structural elements. Each arch is 163 feet long and o ver 23 feet tall. While the new bridge will remain with four traffic lanes, it will be much wider to incorporate lanes outside the arches for pedestrians and cyclists.The plan called for building the precast arches off-site, with expected total bridge closure time of no more than 150 days, according to TxDot, much less than the typical 12 months or more using traditional bridge construction methods.Building the bridge. Image Sundt ConstructionNew ChallengesWhen Sundt took on the project, the design was complete, but there were mucksmuschenstill some issues that had to be resolved, Cedar says. For example, engineers had not decidedhow to build the arches and transport over a million pounds gross vehicle weight over the existing original bridge built in 1913. We had to do a lot of analysis of the existing bridge to make sure we could transport the arches, which were to be placed on columns alongside the existing bridge, he says.Sundt decided to cast the arches on their sides for effic iency and planned for unconventional post-tensioning, or reinforcement of the concrete with cables, by doing so in three stages.There were a lot of challenges associated with the form youd have to provide trying to cast them in a vertical position 23 feet tall, says Cedar.But casting the arches on their sides, which began in 2012 and was completed earlier this year, left a different sort of challengehow to get them vertical without being damaged. A first round of post-tensioning took place once the steel forms were stripped away. Then, Sundt came up with a way to pick up each arch, rotate it to a vertical position, and set the arch on beams. This was followed by another round of post-tensioning, and the arch was slid into a storage area where a third round of post-tensioning took place. The arches remained there until all were cast.When we started, casting the first arch took about six weeks. Cedar says. But by the time we cast the last ones, it was one about every three weeks.Work at the site, installing the drill shafts and columns, took place in spring, and the 12 arches were moved to the site on self-propelled mobile transports over a period of several weeks in May and June and put into place. The bridge closed in June for the final phase, which includes demolishing the old bridge and hanging beams across the arches that will hold the new roadway surface, which is being built in a conventional way.Cedar expects the bridge to be finished in early October and perhaps even sooner. We have 150 days to have the bridge back open, and a $900,000 incentive ($30,000 a day) to get it open 30 days earlier, he says.Nancy S. Giges is an independent writer. For Further DiscussionWe have 150 days to have the bridge back open, and a $900,000 incentive to get it open 30 days earlier.Chris Cedar, Sundt Construction
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.